Eleven Years Without a New Ferry
Washington began building its first new ferry in eleven years this August. How the biggest U.S. ferry system went that long, and why the new boats are hybrids.

I’ve ridden the ferry between Seattle and Bainbridge Island, and between Mukilteo and Whidbey Island.
On Monday, October 5, most of the ferries stopped.
Twenty-three engine room employees called out. By that morning there were no boats at all on Seattle–Bainbridge, Edmonds–Kingston, Fauntleroy–Vashon–Southworth or Port Townsend–Coupeville. Mukilteo–Clinton ran one boat, and half its trips were cancelled. Two of the three San Juan Islands boats were out.
“We currently have 13 out of our 18 boats out of service due to crewing issues,” a Washington State Ferries spokesperson told KUOW.
The two sides told it differently. The ferry system said dispatchers called in substitutes and qualified people declined. The engineers’ union, MEBA, said it had nothing to do with organizing the call-outs, called them “a frantic cry for help,” and pointed to engine crews kept at minimum levels and years of heavy overtime.
By Tuesday morning, Governor Bob Ferguson said service was up and running, with a small number of cancelled sailings. By October 13 he had ordered a new evaluation of the engineers’ salaries, ahead of wage talks with the union in the summer of 2027. “I am committed to the goal of correcting pay disparities between deck and engine,” he wrote to the union.
Engineers start at $130,000 to $169,354 a year, according to KUOW. Staff masters, the captains, start close to $203,000. Wipers and oilers make about $65,000 to $70,000.
That was a crew problem, not a boat problem. But one number in it is worth holding on to.
Eighteen.

The margin
Eighteen is how many boats it takes to run the full domestic schedule. The fleet has twenty-one.
It had twenty-five in 2015. Boats retired and fewer arrived, and by 2025 the count was down to twenty-one. The state says the system needs twenty-six.
Eleven of the twenty-one are more than forty years old. The oldest, the Tillikum, was built in 1959.
Washington State Ferries calls itself the largest ferry system in the United States. It carried about 20.1 million riders in 2025, people and vehicles counted together. Three spare boats is the whole cushion for maintenance, inspections, breakdowns and everything else that pulls a ferry out of service.
One person short
Every boat carries a Coast Guard certificate of inspection, and it sets the smallest crew the boat may sail with. The Coast Guard sets those minimums so there are enough people aboard to handle an emergency.
The ferry system’s own service plan, from April 2026, puts it plainly: “We are budgeted to staff vessels with just enough crew to meet the Coast Guard-minimum COI requirements. This means if even one crew member is missing, the ferry may not be able to sail.” The Legislature has since paid for crews above the minimum, and the ferry system says it is working on putting that in place.
A 2021 report to the Legislature’s Joint Transportation Committee says the ferry system used to schedule one extra standby person per shift, to fill in for a last-minute absence. In 2012 and 2013 the Coast Guard reassessed crewing requirements and raised them. The budgeted crew stayed the same, and the extra person went. The engineers’ union tells it a little differently: it told KUOW the boats used to carry one person above the minimum, and the most recent contract cut it.
The engine room has the largest need. The Coast Guard requires it crewed around the clock, whether the boat is sailing or not. In 2021 that meant at least a chief engineer and one or two oilers on every boat, and an assistant engineer on seventeen of them. In fiscal 2019, engineers and oilers accounted for 47 percent of the ferry system’s overtime spending. The report put the need at 350 engineers year-round. It counted 142 on staff in one place and 177 in another. And the system couldn’t hire them ready-made. Under the union contracts, every new crew member started as an on-call ordinary sailor or oiler, whatever their license.
It ran 97.9 percent of its 3,059 scheduled sailings in the week of November 9 to 15. Of the 67 cancellations, 26 were for weather, 20 for crewing and 13 for the boats themselves.
Two months before the sickout, someone in Florida had started cutting steel for a new one.
The first in eleven years
On August 5, Eastern Shipbuilding Group, in Panama City, Florida, began construction on a 160-car hybrid-electric ferry for Washington. The first is to be named Wishkah.
The state had signed for two with an option on a third. At the ceremony, it took the third.
The contract price for all three is $714.5 million. Add equipment the state supplies itself, construction management, crew training and a contingency for risk, and the total comes to about $1.15 billion. The Legislature had set aside $1.3 billion. Deliveries are scheduled for 2030, 2031 and 2032.
The last time construction began on a new state ferry was May 2015. That boat was the Suquamish, and it went into service in 2018. So the eleven years is the gap between starting boats. The governor’s own announcement counts it three ways: “first new ferry in 11 years,” “the first time in a decade,” and, in the headline, “more than a decade.”
Steel was cut in 2015 and again in 2026, and nothing in between. How?
How it got here
The state has run the ferries since 1951. That year it bought out the Puget Sound Navigation Company, the Black Ball Line, for about $4.9 million: sixteen boats and twenty terminals.
Before Black Ball, there was the Mosquito Fleet, hundreds of small private steamers working Puget Sound and Lake Washington. Estimates of how many run from 700 to 2,500. Steven J. Pickens’s Ferries of Puget Sound is a photo history of those years.
For a long time Washington built its own boats in Washington. State law said so. Under the version in force by 2015, the first request for proposals went only to Washington shipbuilders. The state could look out of state only if every Washington bid came in more than 5 percent over its own engineers’ estimate. State law also required the contracts to be design-build, with the shipyard taking on the design risk and pricing it in, and the award had to go to the lowest acceptable bid.
The Suquamish was the last of the Olympic class, the 144-car diesel boats built under a contract signed in 2007 with Todd Pacific Shipyards, later Vigor. In 2019 the Legislature extended that contract to cover five more Olympic-class boats, hybrid-electric this time.
They were never built. The state’s own estimate for the first one went from $188 million in September 2018 to $249 million in December 2022. The state and Vigor negotiated for three years and couldn’t agree on price or terms. Talks ended in 2022.
So the state started over. That meant a new request for proposals, which by law began in-state, and by the ferry system’s own estimate, a second, out-of-state round would add more than a year.
In 2023 the Legislature changed the law. House Bill 1846 passed 94 to 3 and was signed that May. Out-of-state shipyards could now bid. A Washington builder would get a 13 percent credit, meaning its price would be scored as if it were 13 percent lower.
The new bidding took about a year. Two shipyards bid: Eastern and one in Washington. In July 2025 the state picked Eastern, whose price was more than 30 percent lower. The other bid, the governor’s office says, would have come to $1.51 billion on the same basis, more than $200 million past what the Legislature had appropriated. The contract was finalized in August 2025. Steel was cut a year after that.
Why hybrid-electric
The ferries burn about 19 million gallons of diesel a year. That makes Washington State Ferries the largest producer of greenhouse gases among the state’s agencies, and state law requires agencies to cut emissions 70 percent by 2040 and reach net zero by 2050.
The ferry system’s long-range plan went to the Legislature in January 2019, and an electrification plan followed in early 2021. The plan calls for up to sixteen new hybrid-electric boats, charging at up to sixteen terminals, and converting some of the existing boats. The whole program is estimated at $6 billion. The state has funded about $1.7 billion of it.
Hybrid, not fully electric. The boats keep diesel as a second power source. The ferry system’s reasons: a second source makes the boats more resilient, it gives some control over fuel costs, and it lets the switch start sooner, before every terminal has a charger. Agreements with Seattle City Light and Puget Sound Energy cover the first five terminals: Seattle, Bainbridge Island, Bremerton, Kingston and Clinton.
One conversion is already done. The Wenatchee, one of the three biggest boats in the fleet, went back into service as a hybrid in July 2025. Funding for converting her two sister ships, the Tacoma and the Puyallup, was moved elsewhere in the March 2026 budget, to be revisited as money allows.

Where that leaves the count
The first new boat is due in 2030. The last of the three in 2032. Until then the fleet is twenty-one boats, most of them past forty, running an eighteen-boat schedule.
The Tillikum will be seventy-one in 2030.

Sources and further reading
- Washington breaks ground on first new ferry in 11 years, three hybrid-electric vessels ordered. MyNorthwest, August 5, 2026, for the announcement and the fleet figures.
- Governor Ferguson celebrates the start of construction on first new ferry in more than a decade. Office of the Governor, August 5, 2026, for the contract price, total cost, appropriation, bids, delivery years, the Suquamish dates and the eighteen-boat schedule.
- Puget Sound ferry service returns after Monday shutdown. KUOW, October 5, 2026, for the routes, the thirteen of eighteen, and both sides’ accounts.
- What we know about underlying labor issues that halted WA’s ferry system. Casey Martin, KUOW, October 8, 2026, for the pay figures and the union’s account of the extra crew member.
- Ferguson calls for salary survey after Washington ferry sickout. Jake Goldstein-Street, Washington State Standard, via OPB, October 13, 2026, for the salary evaluation and the governor’s letter.
- Washington State Ferries: Short-Term Strategies for Overtime Reduction. Seattle Jobs Initiative, Segal and Emsi Burning Glass, for the Joint Transportation Committee, December 2021, for the 2012–13 crewing changes, the engine room requirements, overtime, hiring and engineer counts.
- Washington State Ferries Service Contingency Plan. WSDOT, April 2026, for the Coast Guard minimum crew and the quote.
- WSF Weekly Update. WSDOT, November 19, 2026, for the week of November 9 to 15.
- Ferry system electrification. WSDOT, for the plan, its cost, the diesel figure, the terminals, the Wenatchee, and the contract dates.
- Hybrid Electric Ferries: Design-Build Contracting and Procurement. Joint Legislative Audit and Review Committee, 2023, for the procurement laws, the Vigor contract and the cost estimates.
- Final Bill Report, EHB 1846. Washington Legislature, 2023, for the change to the in-state rule and the 13 percent credit.
- Washington State Ferries and Washington State Ferries fleet. Wikipedia, for the 1951 purchase, the Mosquito Fleet estimates, ridership, build years and the name Wishkah.